8Fifteen PMP Study Group

Members of the Silicon Valley PMI Women Project Manager's Group who gather together to study for the PMP certifcation. Our goal is to finish the exam by the end of October 2004. The group was named after the date of our first meeting at the Bean Scene in Sunnyvale. Regular meeting is 9 am Sunday at Starbucks at the corner of Mathilda and El Camino in Sunnyvale. Last meeting held October 17th at Santa Clara Library.

Friday, September 10, 2004

Raj's Formulae

Raj went through the PMBOK and collected the formulae we need to know for the certification test.

Schedule Development

PERT Calculations


Uses values optimistic (O), pessimistic (P), and most likely (M) to determine project duration.
  • Mean = (P + 4M + O)/6
  • Variance = ((P – O) / 6)) 2
  • Expected Value = (O + P + (4 x M)) / 6
    • Example: 60 days most likely, 72 days pessimistic, 48 days optimistic:
    • (48 + 72 + (4 x 60)) / 6

Standard Deviations
  • Standard Deviation = (P – O) / 6
    • Example: 60 days most likely, 72 days pessimistic, 48 days optimistic:
    • (72 - 48) / 6
  • Percent Probabilities
    • 68% ± one standard deviation
    • 95% ± two standard deviations
    • 99% ± three standard deviations

Cost Control
  • PV - Planned Value
  • EV - Earned Value
  • AC - Actual Cost
  • SV – Schedule Variance
  • CV – Cost Variance
  • SPI – Schedule Performance Index
  • CPI – Cost Performance Index
  • BAC – Budget at Completion
  • BCWR – Budgeted Cost for Work remaining
  • ETC = Estimate To Complete
  • EAC = Estimate At Completion
  • VAC = Variance At Completion
Earned Value Managment

  • SV = EV-PV (old BCWP-BCWS)
  • CV = EV-AC (old BCWP-ACWP)
  • SPI = EV/PV (old BCWP/BCWS)
  • CPI = EV/AC (old BCWP/ACWP )
  • BCWR = BAC-EV
  • EAC = AC + BCWR or EAC = AC + (BCWR/CPI)
  • EAC = AC + BCWR or EAC = AC + (BCWR/CPI)
  • ETC = EAC - AC
  • VAC = BAC – EAC
Three approaches to calculating EAC

  • EAC = AC + ETC
  • EAC = AC + BAC - EV
  • EAC = (AC + (BAC – EV) / CPI)

Circular Communication Network

  • (number of participants (number of participants less one)) / 2
  • (n x (n - 1)) / 2
    • Example: six participants
    • (6 x (6 - 1)) / 2


4 Comments:

At Saturday, September 18, 2004 at 8:00:00 PM PDT, Blogger Devans00 said...

Hi May,

I'm glad you find the site useful. To answer your questions.

QUESTION 1: Can the PMP guidelines be used in Agile Programming?

As you probably know, the PMP certification is based on "A Guide to the Project Management Body of Knowledge (PMBOK Guide)". If I'm not mistaken, Agile method applies principles of project management differently than discussed in the PMBOK. Your best bet may to Google the following phrase to see the different theories people have.
PMBOK "agile project management"

At any rate, you should just focus on the PMBOK for the PMP certification test.


QUESTION 2: Does the two terms "mean" and "expected value" have the same meaning?

That's a good question. From what I can tell, when used in some formulas, "mean" and "expected value" do mean the same thing. After Googling the phrase, it seems like it depends on context. I don't know if that answered you 100% but that's my best guess right now.

 
At Thursday, March 8, 2007 at 11:35:00 PM PST, Anonymous Anonymous said...

Thanks
Avinash Kale ( Noida Ke Samsung Wale )

 
At Friday, March 11, 2011 at 6:56:00 AM PST, Anonymous Nathaniel @ project management test questions said...

Nice post.

These different information about various certifications are really interesting.

Thanks a lot for this wonderful post. Keep it up!

 
At Wednesday, August 8, 2012 at 3:17:00 AM PDT, Blogger Penna Sparrow said...

Earned Value Management : Advantages and Disadvantages
Earned Value Analysis terms and Formulae
Earned Value Analysis
Project Crashing & Fast Tracking in Project Management

 

Post a Comment

<< Home


Devans Cosmos Latest

↑ Grab this Headline Animator



Contact

E-mail Me
Download Resume from Scribd


My Other Blogs

Resume

Devans Cosmos

LinkedIn