Remembering Earned Value Formulae
Here is a way to remember at least 4 of the formulae.Step 1
Write down each value (Cost Variance, Schedule Variance,
Cost Performance Index, Schedule Performance Index)
- CV
- SV
- CPI
- SPI
Fill in the equal sign and EV
- CV=EV
- SV=EV
- CPI=EV
- SPI=EV
Step 3
Fill in the operands. Two minus (-) and two divide (/)
- CV=EV-
- SV=EV-
- CPI=EV/
- SPI=EV/
Step 4
Fill in the last variable. AC-PV-AC-PV
- CV=EV-AC
- SV=EV-PV
- CPI=EV/AC
- SPI=EV/PV
Hope this helps,
Raj